this post was submitted on 12 Dec 2025
176 points (98.4% liked)

Technology

77090 readers
2637 users here now

This is a most excellent place for technology news and articles.


Our Rules


  1. Follow the lemmy.world rules.
  2. Only tech related news or articles.
  3. Be excellent to each other!
  4. Mod approved content bots can post up to 10 articles per day.
  5. Threads asking for personal tech support may be deleted.
  6. Politics threads may be removed.
  7. No memes allowed as posts, OK to post as comments.
  8. Only approved bots from the list below, this includes using AI responses and summaries. To ask if your bot can be added please contact a mod.
  9. Check for duplicates before posting, duplicates may be removed
  10. Accounts 7 days and younger will have their posts automatically removed.

Approved Bots


founded 2 years ago
MODERATORS
you are viewing a single comment's thread
view the rest of the comments
[–] mimreos@piefed.social 13 points 2 days ago (3 children)

As pointed out in the article, because datacenters are pretty fast to build, new power plants need to start construction roughly 1 year before the datacenter starts construction. But that leaves the utilities with alle the risk, unless a robust agreement is in place with the datacenter. What happens if several power plants start construction, but the AI bubbles bursts, and the datacenters are cancelled?

[–] humancrayon@sh.itjust.works 13 points 2 days ago* (last edited 2 days ago) (1 children)

Then we get the actual capacity we need at the prices we can afford. Our power grid is disappointing. All that “extra capacity” could stop the random brown outs, rate spikes, and provide some extra capacity for the future.

[–] otacon239@lemmy.world 10 points 2 days ago (1 children)

Are you suggesting we use government resources to benefit the masses? Whose side are you on anyway?

[–] humancrayon@sh.itjust.works 1 points 1 day ago

Damn the man, save the Empire.

[–] Blue_Morpho@lemmy.world 9 points 2 days ago

But that leaves the utilities with alle the risk,

Not if you make the data center pay for it.

If a consumer wants a utility upgrade, the consumer pays all costs upfront. I know this because my neighbor works for the power company and was trying to get gas lines run to our neighborhood. The cost the power company would charge us was hundreds of thousands which even divided by the number of homes meant it would never pay off vs outlr existing cost for propane delivery.

[–] Artisian@lemmy.world 6 points 2 days ago

(Made my day that somebody read the article! I feel like these technical pieces flounder in obscurity.)